Front Stone Wall (Part 2) |
In late 2009, I started work on the east side of the Front Rock Wall. This was going to be a little rock wall to build up the slope in front of the house and frame the Front Walkways. Figured two weekends, four tops. Took eight months. That pretty much spent my rock walling spirit. Then, during the summer of 2010, we had to put stone walls around the Patio (see Patio Part 2 for that three month saga). Now its time to work on the west side of the front wall. Once this is done, I can get on to non rock oriented projects (like the Machinery Shed and replacement of the Leaning Wall of Timbers). |
July 23, 2011. Before. I have 12 tons of crusher run gravel waiting to become the foundation, just like I did on the East End. But there are a few more prep items I have to do. |
The Post Light that we put in many many years ago has to move. There is also a family of little rabbits ("bunnys" at this age) right behind the light post. So I dug a replacement burrow for them to move into. Its lots bigger and has room for all three. |
The final "before" shot. This shows the slope of the front yard that will be flattened when the wall gets built. The rows of rock will be level like the east wall. More chances to use the machines, including the Dump Truck, the EF-3, and the G-Cart. |
Scaped the sod off the top of where the wall trench will go. I've put a little dirt in the Dump Truck. I'm amazed every time I see the volume of dirt that comes from the ground. Its like popcorn - compressed in its native state, fluffy and spacious once its been processed. |
Most of the trenchs are excavated - I have a little to do on the far end. Its about 28" deep. Still a little to do at the far end. |
Today, July 24. The main job was to remove the spoils and clean up the trenches (anything to keep from having to actually start the wall). Here's I'm midway through cleaning off the dirt on the grass and stowing it in the truck for a long, 50 yd. ride to the goat pasture, where the Machinery Shed will go. I can't imagine doing this with a wheel barrow and shovel. Why? Cause I wouldn't. |
Done (for the second time). I have very few excuses for not actually starting to put down stones. I did clean up all the loose dirt and clay that could spill over into the wall zone. |
August 20. Concrete (cheater rock) goes in behind the face rock. What's left of my rip-rap goes in behind. |
View on August 21 after putting in the cheater rock. Nice thing about this phase is that I can keep the rocks on the back side of the work. No more pallets in the road to stop the Fedex trucks.. |
September 11, 2001, the 10th anniversary of a horrfic day in American History. It is also 11 days following the start two years ago of the East End of the Front Wall. I'd guess I'm now about even progress wise. I started this one earlier, but have spent less time on it. I have managed to finish off one pallet of materials and about 4800lbs of cheater rock. |
October 10 and the leaves are changing. Compared to the East Side, I've fallen way behind the pace. One reason may be my need for overkill. Part of that trait is shown here. If a little concrete between the front and back sides is good, then more is better. It costs me about $100 for every 2" of vertical height. |
December 24, 2011 - The wall is put away for a long winter's nap (or until a warm day comes along). Then, I'll place some more rocks. Note the stump on the right is getting shorter and shorter as I test the rebuilt chainsaw. |
All the usable rock is stowed behind the wall. I may place some of it and clean up the back. Then I'll dump the gravel over there in front of the F250 over those pipes in case we get Snow like we did in 2010. |